Champagne Hall upgrades update
The framing work on Champagne Hall is a bit ahead of schedule and the wall was taken down on January 10 to connect to the new space. The electrical rough in should also be completed soon. Drywall work is scheduled to start the week of January 16, along with the plumbing for the new and expanded bathrooms.
As the space is now wide open to the area of construction Champagne Hall will have limited public access and be unavailable for events for the next 4 to 6 weeks to allow the remaining work to proceed. Access to the telephone for residents will remain available.
We hope everybody is able to accept this short period of limited use of the hall during this expansion and we look forward to seeing everyone celebrating the new space once completed.
We will continue to update as work progresses and if anyone has any questions please feel free to contact me.
Kwänaschis – Thank You.
Craig Hampton, Capital Projects Manager